Pavement Moratorium
The City places moratoria on all public roadways, as defined in HBMC Section 12.09, that have been recently maintained or reconstructed. Each moratorium goes into effect following construction and is in place for the following periods:
- Three years following roadway maintenance, including but not limited to chip seal, cape seal, slurry seal, micro paving, or other maintenance of asphalt concrete roadway;
- Five years following roadway construction, including but not limited to reconstruction, grind and overlay, or other replacement of asphalt concrete roadway; and
- Ten years following roadway construction, including but not limited to, reconstruction of Portland cement concrete roadway.
Further details regarding the pavement moratorium, including the application process for a waiver, can be found in the Pavement Moratorium Guidelines document.
Prior to performing any work in the public right-of-way, issuance of a right-of-way permit by the Public Works Department is required. For information about right-of-way permits, visit the City's website here.
The following is a list of streets currently under moratorium:
Areas of the Public Right-of-Way Under Moratorium
Street |
Segment Start |
Segment End |
Moratorium End |
11th Pl |
Cul de sac |
PCH |
November 2026 |
19th St |
Prospect Ave |
Harper Ave |
November 2026 |
20th Pl |
Prospect Ave |
Harper Ave |
November 2026 |
20th St |
Prospect Ave |
Harper Ave |
November 2026 |
21st St |
Prospect Ave |
Harper Ave |
November 2026 |
24th St |
Park Ave |
Valley Dr |
November 2026 |
24th St |
Prospect Ave |
Harper Ave |
November 2026 |
25th St |
Manhattan Ave |
Myrtle Ave |
November 2028 |
Ardmore Ave |
8th St |
Pier Ave |
November 2026 |
Aubrey Ct |
Cul de sac |
Aubrey Park Ct |
November 2026 |
Aubrey Park Ct |
Aviation Blvd |
Cul de sac |
November 2026 |
Harper Ave |
Palm St |
Artesia Blvd |
November 2026 |
Gould Terrace |
Ardmore Ave |
Gould Ave |
November 2026 |
Montgomery Dr |
Aubrey Park Ct |
Ocean Dr |
November 2026 |
Ocean Dr |
Aviation Blvd |
14th St |
November 2026 |
7th St |
PCH | Prospect Ave | April 2029 |
17th St |
Prospect Ave | Cul de sac | April 2029 |
Golden Ave |
Southerly terminus | Northerly terminus | April 2029 |
Prospect Ave |
South City Limit | Artesia Blvd | April 2029 |
The following is a tentative list of streets planned for upcoming pavement work. This list is subject to change:
Areas of the Public Right-of-Way Anticipated in Upcoming Pavement Projects
Street |
Segment Start |
Segment End |
Anticipated Construction |
Parking Lot A |
N/A |
N/A |
2025 |
Valley Dr |
Pier Ave |
Herondo St |
2025 |
Pier Ave |
Hermosa Ave |
PCH |
2025 |
9th St |
Ardmore Ave |
PCH |
2025 |
11th Pl |
Prospect Ave |
Harper Ave |
2025 |
14th St |
Ocean Dr |
Prospect Ave |
2025 |
15th St |
PCH |
Ocean Dr |
2025 |
16th St |
Ardmore Ave |
PCH |
2025 |
Ocean Dr |
14th St |
15th Pl |
2025 |
Power St |
20th St |
24th St |
2025 |
Please check this webpage on a frequent basis, as the list will be regularly updated as current projects are completed and upcoming projects are planned.