Pavement Moratorium

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Paving snapshot

Pavement Moratorium

 

The City places moratoria on all public roadways, as defined in HBMC Section 12.09, that have been recently maintained or reconstructed. Each moratorium goes into effect following construction and is in place for the following periods:

  • Three years following roadway maintenance, including but not limited to chip seal, cape seal, slurry seal, micro paving, or other maintenance of asphalt concrete roadway;
  • Five years following roadway construction, including but not limited to reconstruction, grind and overlay, or other replacement of asphalt concrete roadway; and
  • Ten years following roadway construction, including but not limited to, reconstruction of Portland cement concrete roadway.

Further details regarding the pavement moratorium, including the application process for a waiver, can be found in the Pavement Moratorium Guidelines document.

Prior to performing any work in the public right-of-way, issuance of a right-of-way permit by the Public Works Department is required. For information about right-of-way permits, visit the City's website here.

The following is a list of streets currently under moratorium:

Areas of the Public Right-of-Way Under Moratorium

Street

 Segment Start

Segment End 

Moratorium End 

 11th Pl

 Cul de sac

 PCH

November 2026 

 19th St

 Prospect Ave

Harper Ave 

November 2026 

 20th Pl

 Prospect Ave

 Harper Ave

November 2026

 20th St

 Prospect Ave

 Harper Ave

November 2026

 21st St

 Prospect Ave

 Harper Ave

November 2026

 24th St

 Park Ave

 Valley Dr

November 2026

24th St 

Prospect Ave 

Harper Ave 

November 2026 

25th St 

Manhattan Ave 

Myrtle Ave 

November 2028 

Ardmore Ave 

8th St 

Pier Ave 

November 2026 

 Aubrey Ct

Cul de sac 

Aubrey Park Ct 

November 2026 

 Aubrey Park Ct

Aviation Blvd 

Cul de sac 

November 2026 

Harper Ave 

Palm St 

Artesia Blvd 

November 2026 

 Gould Terrace

Ardmore Ave 

Gould Ave 

November 2026 

 Montgomery Dr

Aubrey Park Ct 

Ocean Dr 

November 2026 

 Ocean Dr

Aviation Blvd 

14th St 

November 2026 

7th St

PCH  Prospect Ave  April 2029 

17th St

 Prospect Ave Cul de sac  April 2029 

Golden Ave 

Southerly terminus  Northerly terminus  April 2029 

 Prospect Ave

South City Limit  Artesia Blvd  April 2029

 

The following is a tentative list of streets planned for upcoming pavement work. This list is subject to change:

Areas of the Public Right-of-Way Anticipated in Upcoming Pavement Projects

Street

Segment Start

Segment End

Anticipated Construction

Parking Lot A

N/A

N/A

2025

Valley Dr

Pier Ave

Herondo St

2025

Pier Ave

Hermosa Ave

PCH

2025

9th St

 Ardmore Ave

PCH

2025

11th Pl

Prospect Ave

Harper Ave

2025

14th St

Ocean Dr

Prospect Ave

2025

 15th St

PCH

Ocean Dr

2025

16th St

Ardmore Ave

PCH

2025

Ocean Dr

14th St

15th Pl

2025

Power St

20th St

24th St

2025

 

Please check this webpage on a frequent basis, as the list will be regularly updated as current projects are completed and upcoming projects are planned.