This project is funded by the sewer levy fees.
From January 24, 2022 , to January 28, 2022, point repairs will continue on 19th St, between Hermosa Ave. and Manhattan Ave.; Bayview Dr., between Pier Ave. and 10th St.; and 3rd Ct., between Beach Dr. and Hermosa Ave. with a new maintenance access hole.
Pipe lining of sewer main on Owosso Ave. between Aviaton Blvd. and 14th St., 7th S.t and Prospect Ave., Campana St. between Joy St. and Prospect Ave., and on Prospect Ave. between 10th St. and 11th St.
Prior Construction Updates:
- January 10 - 21, 2022
Point Repairs will occur on Clark Field, Aviation Blvd between Owosso Ave and Aubrey Ct, 7th Pl between Prospect Ave and Reynolds Ln, 19th St between Hermosa Ave and Manhattan Ave, Bayview Dr between Pier Ave and 10th St, Prospect Ave between 16th St and 15th St. Also, two new maintenance access holes will be installed on 3rd Ct between Hermosa Ave and Beach Dr.
- December 13 - 17, 2021
Any questions or additional information, please contact the Project Manager, Andrew Nguyen.
View map of planned Phase 1 and Phase 2 of CIP 421
View map of completed and planned sewer projects
Project Completed: July 2020
The City of Hermosa Beach has contracted with MNR Construction, Inc. to perform sewer repair work throughout the City. The project includes root removal, sewer lining installation, repair, and replacement of approximately 11,000 feet of sewer segments in four major areas of the City. The areas include the northwest portion of Hermosa Beach; the northeast portion of Hermosa Beach, immediately south of Artesia Boulevard and east of Pacific Coast Highway; the southwest portion of Hermosa Beach, along Hermosa Avenue between 1st Street and 8th Street; and, near the intersection of Park Avenue and Loma Drive. This project also includes lining, repair, and replacement of approximately 60 defective maintenance access holes.
Current Status:
- Completed
Construction Updates:
- For April 2020: Project Closeout
- For February 2020 to March 2020: Sewer frames and covers replacement. Grinding and pavement of trenches. Lining of sewer mains.
- For December 2019 through January 2020: Sewer maintenance access holes removal and replacement.
- For November 4 through November 22: CCTV recording and cleaning of sewer main. Construction of point repairs and removal and replacement.